WORK STEPS | PERFORMER | REFERENCE |
Project Functional Safety Manager |
Item definition FS concept |
|
Project Functional Safety Manager |
||
Specification of TSReqs via derivation from functional SReqs, considering dependencies within item and between item and surrounding. TSReqs shall be allocated to elements of system design. ISO 26262-4 (Handbook chapter 4.1). |
||
Project Functional Safety Manager |
||
If wanted/ needed, ASIL decomposition could be integrated here. ISO 26262-9 5 (Handbook chapter 9.1). |
||
Project Functional Safety Manager |
Technical safety requirements |
|
Project Functional Safety Manager |
Technical safety concept |
|
Project Functional Safety Manager |
||
Specify system design considering preliminary system architecture as well as technical safety concept. Ensure testability of components at phase of
integration, specify internal and external interfaces. Architecture shall comply with highest corresponding ASIL. ISO 26262-4 (Handbook chapter 4.2.1). |
||
Project Functional Safety Manager |
System design specification |
|
Project Functional Safety Manager |
||
To avoid systematic failures, well-trusted automotive design principles shall be applied: reuse of well-trusted technical safety concepts, element designs
including HW and SW components, mechanisms for failure detection and control, standardised interfaces. Use deductive and/ or inductive analysis, dependent
on ASIL. ISO 26262-4 (Handbook chapter 4.2.3). |
||
Project Functional Safety Manager |
Safety analysis report |
|
[TBD] neues Bild mit "Specification of measures for control of random HW failures" [TBD] |
Project Functional Safety Manager |
|
Measures for detection and control or mitigation of random HW failures shall be specified with respect to system design. ISO 26262-4 (Handbook chapter 4.2.4). |
||
Project Functional Safety Manager |
||
The HSI shall be specified considering their interaction with one another, including HW devices controlled by SW and HW resources supporting SW execution, all being compliant with the technical safety concept. ISO 26262-4 (Handbook chapter 4.2.5). |
||
Project Functional Safety Manager |
HSI specification |
|
Project Functional Safety Manager |
||
Diagnostic features enabling field monitoring during operation shall be specified. Requirements for production, operation, service and decommissioning have to be specified including assembly instructions, safety-related special characteristics,
proper identification of systems or elements, verification methods and measures for production, diagnostic data and service notes, decommissioning. ISO 26262-4 (Handbook chapter 4.2.6). |
||
Project Functional Safety Manager |
Requirements specification |
|
Specification of requirements for production, operation, service and decommissioning. | ||
[TBD] Hier Prozesselement durch "Verification of technical safety concept and system design" ersetzen [TBD] |
Project Functional Safety Manager |
09_VERIFICATION |
Completeness and compliance of system design with technical safety concept shall be verified. ISO 26262-4 (Handbook chapter 4.2.7). |
||
[TBD] Hier Prozesselement durch "System integration and testing" ersetzen [TBD] |
Project Functional Safety Manager |
|
Planning and performance of integration and testing, distributed into HW-SW integration, system integration and vehicle integration. Integration performance and test cases shall be specified. ISO 26262-4 (Handbook chapter 4.4). |
||
[TBD] Hier Prozesselement durch "Integration and test strategy" ersetzen [TBD] |
Project Functional Safety Manager |
Integration and test strategy |
[TBD] Hier Prozesselement durch "Integration and test report" ersetzen [TBD] |
Project Functional Safety Manager |
Integration and test report |
[TBD] Hier Prozesselement durch "Safety validation specification" ersetzen [TBD] |
Project Functional Safety Manager |
09_VERIFICATION |
The safety validation shall be planned considering ISO 26262-6 Annex C (if applicable), validation procedures, test cases and further aspects listed in reference below. ISO 26262-4 (Handbook chapter 4.4.1). |
||
[TBD] Hier Prozesselement durch "Safety validation specification" ersetzen [TBD] |
Project Functional Safety Manager |
Safety validation specification |
Project Functional Safety Manager |
09_VERIFICATION |
|
The safety goals shall be validated for the item as planned. Consider references below. ISO 26262-4 (Handbook chapter 4.4.2). |
||
Project Functional Safety Manager |
Safety validation report |